The SR 536 Skagit River/Division Street Bridge has been closed to cars in both directions since Sunday, Nov. 1. A driver going from downtown Mount Vernon to West Mount Vernon now follows a signed detour of about 10 miles between the two ends of the bridge. Someone on foot can still get across the 675-foot bridge, on the sidewalk for most of the closure and by free shuttle when work closes it. A full closure is also the shortest way to finish this project. The city and the state chose it on purpose and kept a way across the river open for people the whole time.
Four months of half a bridge, traded for two weeks of none
The full closure ended a much longer arrangement. Eastbound SR 536 traffic has been barred from the bridge since June 11, while crews worked on the larger eastern span. Under the original schedule, that eastbound-only closure would have stayed in place until early 2027, ahead of the Skagit Valley Tulip Festival.
| Original plan | Current plan | |
|---|---|---|
| Who could cross | Westbound traffic only, since June 11 | No passenger or freight vehicles in either direction |
| Expected finish | Early 2027, before the Tulip Festival | About two weeks after the Nov. 1 start, aimed at Thanksgiving |
| What decides the date | The construction schedule | Rain, wind and cold |
WSDOT counted about 18,000 vehicles a day on the bridge in 2024, split nearly evenly between the two directions. That means about half of those trips have been taking the detour since June. The new plan adds the other half for roughly two weeks and in return ends the project close to four months early, according to WSDOT's September 24 announcement.
The business case appears in the same release. Mount Vernon Mayor Peter Donovan told WSDOT:
"This is a solution that prioritizes the small business community in Mount Vernon. We are so grateful for WSDOT's openness to pursuing this expedited path forward. Wrapping up the project before the holiday business season could be the difference in those businesses' survival."
The City of Mount Vernon's notice says the city took the idea to the groups that would feel it most before agreeing. Those groups were west side businesses, the Mount Vernon Downtown Association, the Skagit Valley Chamber of Commerce, the Mount Vernon School District, Skagit Transit and the city's first responders. According to the mayor, all of them decided that a hard two weeks was worth having the bridge fully open before holiday travel and shopping started.
Why the switch could happen this fall
The bridge has two spans, and that is why the plan could change halfway through. Under containment tarps that kept debris out of the Skagit River, crews blasted paint and debris off the larger eastern span, repaired and replaced steel pieces, and sprayed on new coats of paint. Removal of those tarps began on Tuesday, Sept. 22. The containment system then had to be rebuilt around the smaller western span. WSDOT called that changeover "a unique opportunity" to finish the rest of the work faster with one short full closure. Melissa Ambler, WSDOT's assistant region administrator for the Mount Baker area, credited the contractor's willingness to change the traffic control plan this late in the project.
The bridge was built in 1953 and had not been painted since 1990. The Skagit Valley Chamber's closure notice lists the work scheduled for the closure window:
- Finish painting the bridge
- Repair the driving surface
- Seal the bridge joints
- Install lane markings
- Take down the containment system that has protected the river during construction
- Return the bridge to its usual layout of one lane in each direction
WSDOT also says the deck repairs are meant to make the crossing smoother once cars return.
The crossing that never closed
This is the part of the closure most worth knowing about. Pedestrians, bicyclists and people using mobility devices keep access across the river in both directions. According to WSDOT's project page, the sidewalk stays open for most of the closure. When work requires closing it, a free ADA-compliant shuttle picks people up on both sides of the river.
For drivers, things are more involved. Both directions use the signed detour of Avon Allen Road, SR 20 and I-5. Eastbound drivers head north on Avon Allen, east on SR 20 and south on I-5, and westbound drivers do the same in reverse. Temporary signals stand at each end of the bridge, and they are easy to misread. They serve only emergency vehicles, which carry switches that trigger them, and they will not change for passenger or freight traffic. Emergency responders can cross in both directions throughout the closure.
Bus riders are also rerouted. Skagit Transit's detour alert says Routes 40X and 615 detour in both directions starting Sunday, November 1, for an expected two to three weeks, with significant delays. The transit agency's estimate runs a little longer than WSDOT's two-week goal, so the detour may outlast the bridge closure by a few days.
Weather sets the reopening date
Every official notice about the closure says the reopening depends on the weather. WSDOT's goal is to reopen both directions about two weeks after the closure began, in time for the holiday season. Rain, wind and cold could delay the work and stretch the closure. Contractor crews tried to finish most of the work that needs dry weather before the full closure started, but some remaining tasks could still slip. WSDOT also lists unexpected resource problems as something that could extend the closure.
Reopening does not mean every crew leaves on the same day. WSDOT expects no long-term lane closures after the bridge reopens, but contractors may keep working through the end of the year to finish remaining tasks and move equipment out. The project page lists the full timeline as December 2022 through fall 2026.
WSDOT posts progress updates on its regional X and Bluesky accounts. Live road status is on the WSDOT mobile app and the WSDOT travel map.
The weekend at the two-week mark
Two weeks from the Nov. 1 start lands on Sunday, Nov. 15, so the target reopening falls on the same weekend as one of the busiest days on the early holiday calendar, Saturday, Nov. 14.
That evening, the Mount Vernon Downtown Association holds Ladies Night Out from 6 to 9 p.m. Fourteen downtown businesses take part, pouring more than 30 wines from wineries around the state, and ticket holders get access to promotions across the district. The Downtown Mount Vernon events page bills it as a way to start holiday shopping early while supporting local businesses.
Earlier the same day, the Valley Made Holiday Market runs from 10 a.m. to 4 p.m. at Hillcrest Lodge, 1717 S. 13th St., with more than 35 local makers and artists. Christianson's has a holiday market in its Vinery on Nov. 14 and 15 from 10 a.m. to 4 p.m., and another on Dec. 12 and 13 with the same hours.
The bridge could reopen that weekend or later, depending on the weather. Either way, people walking from West Mount Vernon to the Ladies Night Out stops downtown can still cross the river, on the sidewalk or by the shuttle if work has closed it.
The rest of the season is already on the schedule. The Holiday Parade & Tree Lighting starts at 5 p.m. on Sunday, Dec. 6, on S 1st Street. The MVDA produces it with help from the City of Mount Vernon, and WECU sponsors it. If WSDOT stays on schedule, cars will be crossing the river in both directions again by parade night, which hasn't been possible since June 11.
A river crossing shapes daily routines more than most people expect until it closes. That holds for Mount Vernon's two halves, and it holds across Skagit County, where the drive to work, the grocery run and an evening downtown all depend on a few bridges. If you're weighing where to live in the valley and want to talk through how those routes play out, Rob Skelton is glad to help. Request a free consultation, and we'll map out the details together.